Thursday, December 3, 2009
Pictures 12-2-09
Work is going well but frustrating with all the recent rain. Work continues with the irrigation system being installed, bridge pilings and some earth moving. Pre-load areas almost complete with the exception of the landing area in front of 8th tees. This final pre-load is a very difficult site to move material to and is time consuming using the smaller tip carts. The bridge pilings are being installed and should all be installed in the next two weeks. The decking will immediately follow the pilings.