Wednesday, October 28, 2009

Work has begun

Now that we were given permission to start earthwork from both Hingham and Cohasset conservation commission's earth is being moved.  The first order on the schedule is to pre-load the designated deep peat areas (4 in total) and leave in place for 100 days. 



Looking to the right of 6 green-this will be a compensatory storage area




You will also notice the amount of tree work that is needed in these earthmoving areas.  Irrigation work is also started with the existing irrigation heads being removed and new pipe is being welded together for installation.




This was taken from the front of 9 tee.  Notice tree removal on the right side.



Tree removal for cut on the right side of hole 5