It’s been cold and work continues. Equalization pipes on holes 7 and 9 are being installed to balance the water between compensation areas and the drainage ditch per conservation. There are two pipes (side by side) on hole 9 and one on hole 7. There is also going to be a pipe on hole 5 and that will start at a later date.
The bridge is also still being constructed. Most piling has been installed and decking has started. This is going to be a very attractive bridge adding style to the 8th hole tee complex. Once complete this bridge will be 570 feet long and 12 feet wide. The white tee as well as the yellow tee is being constructed on decking to secure their elevation.
Please post a comment or email me if you have any questions or would like to see the project first hand.
Glen
Equalization pipe being installed on hole 7
Equalization pipe being installed on hole 7
Equalization pipes being installed on hole 9
#8 Bridge Decking started
Bridge wing wall at blue tee
Pile caps and stringers being installed









